Shawnee High School Additions and Alterations

LOCATION:
Medford, New Jersey
DESIGN / BUILD / COMPLETION DATE:
October 2009
PROJECT DESCRIPTION:
Additions to Shawnee High School
  • New 944-seat Auditorium
  • New 8 Classroom Addition
Alterations to Shawnee High School:
  • Child Study Team / Nurse Suite
  • Mechanical / Electrical Room
  • Boys / Girls Locker Rooms
  • Gymnasium

RAI furnished and installed the complete electrical portion of the project, including: power distribution system, lighting, power distribution to all equipment, fire alarm systems, clock system, sound system, and data-com systems.

RAI scope included, but was not limited to:

  • Electrical permitting
  • Furnish and install distribution equipment
  • Furnish, install and test new emergency generator
  • Furnish and install all secondary power distribution
  • Furnish, install, test and certify new fire alarm systems for the entire school
  • Furnish and install all lighting in the building and additional site lighting
  • Furnish and install a new data-com system for the entire building
  • Furnish and install a new clock and sound paging system for the entire building
  • Furnish and install complete stage lighting and dimming system for the auditorium